top of page

Cisumdawu Toll Road (Phase II) Project

cisumdawu.jpg

Project Location

West Java Province

Client

Ministry of Public Works and Housing (MPWH)

Services Period

From August 2016

to December 2019

Type of Services

Construction Supervision

Project Overview

The Project scope is the supervision of construction of the Cisumdawu Freeway (Toll Road) Project Phase II, including:

 

  • 10.7 Kilometers length of Main Road with Tunnel construction (± 500 meters),

  • Access Roads of Rancakalong Interchange (± 1100 meters),

  • Access Roads of Sumedang Interchange (length± 1000 meters) and

  • 2 bridges (total length ± 970 meters).

 

The Consultant Team performs technical supervision of the construction in the field according to the standards and criteria for the road / bridge / tunnel undertaken by the contractors.

 

Typical duties and services being provided include:

  • Reviewing and approving the Contractor’s working drawings;

  • Reviewing the work schedule and progress;

  • Evaluating the suitability of all project inputs;

  • Inspecting and evaluating installations;

  • Verifying the survey data;

  • Implementing effective and control of the quality of the carried-out work; and

  • Revising the design, if there is a discrepancy with the field conditions.